• Kitchen

    Project Noe Completed

    We are pleased to report that the Project Noe house was completed as planned in late May 2010. It’s interesting to note that despite the economy, the Project Noe home was already under…

    Related Posts Plugin for WordPress, Blogger...
Featured Project
  • Late April 2010

    Late April 2010

    By the end of April 2010, the Project Noe house is only a few weeks away from completion. The front door is now installed and is ready for some paint. The garage door…

  • Mid March 2010

    Mid March 2010

    A few weeks after our last post, changes included the installation of the Seagrass marble counter tops on the kitchenette/bar in the lower level. All the tiling in the lower level bath is…

  • Early March 2010

    Early March 2010

    By early March 2010, the garage door was installed, but still had to be painted black as does the trim around it. You can also see the small hedges were planted in front…

  • Mid January 2010

    Mid January 2010

    By mid January, the exterior of the Project Noe house is nearly complete. The cedar shingles were carried down to the street level, the trim around the garage will be painted black. Along…